Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Curb
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 63 Lo 42

Reith Riley had a concrete crew pouring the side walk on the west side of Saint Joe between Colfax and LaSalle. They then went and poured cycle track on the East side Main street between Jefferson and Washington.  A second crew poured the concrete pavement on the South West corner of Colfax and Saint Joe. They then went and poured sidewalk at the South West corner of Main and Western.  

A prep crew worked on placing the patching between the curb and cut out on saint Joe from Colfax to LaSalle on the west side of the road. A second prep crew worked on prepping for cycle track between Jefferson and Wayne on the east side of Main. A third crew worked on placing cycle ban on Michigan from LaSalle to Marion east side. Asphalt crew paved from western to just short of LaSalle

Indiana Earth worked on removals on Washington street for structure 164, They then moved to the east side of Saint Joe. They also worked on placing the 53's on Main street for the brick pavers between the curb and side walk.

Slussers worked on placing edging down on Bartlett west of Michigan. They also prepped for sod South of Marion on Main and Michigan. They also laid out for trees on Marion and on Bartlett. They then placed sod at Marmain and worked south on the west side of Main Street.

Wisco worked on the east side of Michigan between LaSlle and Marion.

Pemberton Davis had a crew working excavating for foundations on the west side of Saint Joe from Bronson to LaSalle

Air marking worked on laying out traffic markings on Michigan from Sample to Western. They also worked on traffic Markings with the push cart from Ewing to Sample on Main Street and Michigan.