Wednesday, October 12, 2016

10-12-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing: Asphalt
Fraction of Day workable 10/10
AM Mostly Cloudy PM Cloudy Rain 4 pm
Hi 74 Lo 58

Reith riley had a Paving crew pull the approaches on Main Street west side Western and Monroe east side Monroe, Western, Wayne, Jefferson and Colfax. They also fog sealed Main Street.

Reith Riley had a prep crew working on grading out for he Pave Drain on the east side of Main from Wayne to Western. The second crew worked on placing pave drain on the east side of Main from Jefferson to Wayne.

Reith Riley had a Concrete crew working on the North east corner of Main and Washington. They had a second crew working on the North west corner of Jefferson and Main. A third crew worked on the South west corner of Wayne and Main. 

Pemberton Davis worked on the poles at Washington and Main. They also had a crew working on setting light poles on the west side of Main from LaSalle to Washington.

Indiana Earth worked on grading out From  Colfax to LaSalle on the east side of Saint Joe. they also worked on removing the asphalt for the islands on Saint Joe.

Woodruff worked on setting structures between Washington and Colfax on the west side of Saint Joe.

Air Marking had a crew doing layout on Main street from LaSalle to South Street. they had a second crew working on epoxy painting from Bronson to South Street on Main Street. A third crew finished the long line on Michigan from Ewing to Sample. A Fourth crew worked on detail work from Sample to Ewing on Main and on Michigan.

Did not have Wisco or Slussers on site today