Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Drizzle PM Cloudy Drizzle
Hi 38 Lo 32
Reith Riley had a concrete crew work on pouring the North East and South west corner of Michigan and western. A second crew worked on miscellaneous pours through out the job all the way to Angela.
Reith Riley had a brick cutting crew working on the west side of main from Wayne to Western. a stone crew worked the east side of main between Jefferson to Washington. A brick laying crew worked the east side of Main from Jefferson to Washington.
Indiana earth worked on cutting out from LaSalle to Madison on the east side of Michigan for brick. They then cleaned up South of LaSalle on Saint Joe on the east side.
Slussers placed sod on Main Street from Madison to LaSalle on the east and west side. They then worked on Michigan from LaSalle to Marion on the east and west side of the road.
Pemberton Davis poured the foundations on the east side of Saint Joe at Jefferson. They also worked on the conduit at western and Main South west corner.
Air Marking was on site and did removals at western and Main on Lafayette and LaSalle they also did removals on sample east of Main.
Meeting MINUTES
Meeting With:
|
Reith
Riley & City of South Bend
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
Two
Way Conversion Weekly Progress Meeting
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Traffic Closure Updates: Crews will just be
closing a lane where they are working and putting out barrels to direct traffic
around them. Pemberton Davis will be closing Washington Street when they do
signal work there for safety.
Utility Relocation Issues:
AEP: Was not at the meeting
Robert Henry: Was not at the meeting
1.
Michigan St. will be open by 4pm today for the
weekend and will close again on Monday.
2.
Vault at Main and Washington S/E Corner
NIPSCO/InfraSource: Was not at the meeting
Water Dept: Had questions
about snow removal at their office on Main and Colfax. Everything should be
fine, and they were asked to keep the salt use to a minimum
Transpo: Asked about light
timing, which will be an ongoing process and when the traffic signal at
Michigan and South street will be in. Hopefully by Christmas.
Metronet: Was not at the meetin
1. WIFI
on Saint Joe and Main. Nothing has been done with this yet.
Utilities Q/A: Grinding and striping was brought up on
Sample St. which should be happening today. 311 also asked about left turn
lanes on Sample to turn onto Michigan and Main streets. This has to happen
through INDOT though because it is a state highway.
INDOT: Questions:
Stakeholder
Questions: The signs on Michigan by Angela heading south that say the road
is open to the hospital can now come down. The hospital asked when the railings
for the stairs and gate for dumpster pad are going in. Measurements have been
taken and they are being fabricated off site. The no parking signs on Bartlett
are to be put back up. The hospital also wanted to know when the striping for
the parking garage entrance will be done, which may not happen until spring.
They also asked to check if the project has outlets going in next to the trees
for Christmas lights.
10:00 am 10:10 Break Utility
and Stakeholders can leave
Action Items
1
Upcoming
work for the week: Brick pavers on Main St. and curb ramps on St Joe/Michigan.
Pemberton Davis will be working on traffic signals.
2
Western
and Main South West Corner: Will start on Monday, should be done by Wednesday
3
Scheduled
\opening
A. Traffic
Signals Jefferson\Washington: Beginning work on Jefferson on Wednesday, and
Washington right after that. They will be closing Washington between Michigan
and St. Joe while working on the intersection.
B. Markings:
Trying to get in the most important ones before winter.
4
Chippewa walk trough/ Traffic signal work: The
walk through will be Wednesday Dec. 7th from 1-3pm. Meeting in the
Palmer funeral home parking lot
5
Snow Flags have been ordered and are at the
border waiting to come through customs.
6
Main Street Bridge lighting: Pemberton Davis
will have a quote in today and once it is approved will order the lights and
install them as soon as they come in. One to two day project, and will have a
separate service crew installing them.
7
Getting
ready for Winter/expectations
A.
Cross walks: Hope to have one concrete one
in at each intersection. Will keep working on them and temporarily fill with
stone any that don’t get poured before winter.
B.
Clean Man Holes: On the list of things to
do
C.
Temp Tape removal on the list of things to
do
D.
Behind curb drop-offs
E.
Signs on 31 will be taken care of. Didn’t
take them down this week because of concerns of getting stuck in the ditch with
how rainy it has been.
Reith Riley Construction
Concerns/Questions: Will need access to the area in front of the Chase
tower and the new Marriott hotel by May 1st in order to complete
everything by June 1st
City
Concerns/Questions: Made sure that
Pemberton Davis will work on getting street lights up on one side of St. Joe
before finishing the second side of Main St.
Next weekly progress meeting ?