Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy 
Hi 40 Lo 30

Reith Riley had a concrete crew working at the South West corner of Main and Western. a Second crew is working on the South West corner of Jefferson and saint Joe they then went to the South east corner of Jefferson and saint Joe, A third crew worked on the South east corner of Michigan and Jefferson/Wayne, They then worked on the South West corner of Jefferson/Wayne and Michigan. 

Reith Riley had a crew placing brick on the south west corner of Colfax and Main. A second crew worked on Main Street from Jefferson to Wayne on the east side. 

Indiana Earth was working on the paver base at the intersection of Jefferson and Saint Joe.

Pemberton Davis worked on setting strain poles at the intersection at of Jefferson and Saint Joe. They also worked on conduit at Western and Saint Joe. They were also installing the pucks for the LaSalle/Main street intersection.

Slussers was on site and planted trees on Main a street from LaSalle to Wayne on the west side of the road,

Air Marking was in and Temporary stripped the turn lane on Sample and they temporary stripped Madison from Lafayette to Michigan. 