Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy Snow/Rain PM Cloudy Rain
Hi 36 Lo 28
Pemberton Davis showed up and worked on South and Michigan. They left at 11:00 am after getting soaking wet.
There were 7 employees on site that were hand digging and placing conduit.
No other work took place today.
Phil @ Pemberton; "Michigan and South St. ; still installing underground conduit around intersection. Then got rained out."
Pemberton Davis showed up and worked on South and Michigan. They left at 11:00 am after getting soaking wet.
There were 7 employees on site that were hand digging and placing conduit.
No other work took place today.
Phil @ Pemberton; "Michigan and South St. ; still installing underground conduit around intersection. Then got rained out."