Thursday, January 26, 2017

1-26-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy Snow PM Cloudy Snow 
Hi 35 Lo 30

Pemberton Davis worked on pulling wire for the street lights on the east side of Saint Joe from Colfax to LaSalle and on Saint Joe from Wayne to Washington on the east side. They also finished setting the poles on the east side of Saint Joe from Wayne to Jefferson.

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; installed lighting cable north of Wayne to Jefferson and north of Colfax to LaSalle. Set more poles at same locations. Spliced poles as well. 
MLK and Jefferson; set pedestrian signals around intersection (6)."