Wisco had a 4 man crew working on the east side of saint Joe from Washington to Wayne.
Slussers had a 2 man crew placing trees on Main Street.
AirMarking had a 2 man crew working on the crosswalks on Main street doing the center turn land on Jefferson, Washington Colfax and Madison.
Meeting Min
Meeting With:
|
Reith
Riley & City of South Bend
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
Two
Way Conversion Weekly Progress Meeting
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1.
Reith Riley-Plans on finishing the concrete work
at the intersection of Navarre, Monroe, Wayne Street and Colfax on Saint Joe
St. / Michigan. They also plan to do the concrete work in front of the Century
Center in the coming week. Along with having, Indiana Earth come back in and
work on the parking area by McDonalds and the topsoil areas on Saint Joe
Street. Slussers will be in to work on Landscaping. They will also finish up
Division A punch list in the next couple of weeks.
2.
Pemberton Davis Will be at Wayne and MLK Monday
doing the controller cabinet. They will then work at Navarre and Michigan walk
waits and push peds. Work at western and MLK, and Finish Colfax and MLK\
Utility Relocation Issues:
AEP:
1.
Power at Western and Michigan – Should be Monday
2.
Power at Monroe and Michigan- no AEP Rep today
3.
Both Bronson Streets
4.
Michigan and Indiana
Robert Henry:
1.
Manhole lid at Main and LaSalle – This will be
done on April 29th and opened back up on April 30th.
2.
Wayne/Jefferson and Saint Joe/MLK South East
Corner – that is the Trinity Towers vault and I will have Reith Riley lower the
structure.
Metronet: Had concrete get
in a fiber man hole and will have to chip it out and back charge Reith Riley.
Metro Net still has to get the WIFI hooked up at Colfax and MLK and that will
then be completed.
Transpo- No questions
311
Utilities Q/A
INDOT: Questions:
Stakeholder Questions:
Memorial HospitalI had a list.
1) There is concrete slurry on the
windows and aluminum panel on the North side of 100 Navarre Place bldg . that
needs cleaned off.
2) When replacing dead trees we do not
want any species that has thorns on them. The dead tree at the Hospital’s
entrance near Bartlett St. had thorns in it .
3) Is it the Hospital’s responsibility
to start mowing the grass along the South side of Bartlett, North/south side of
Marion, etc. It is getting long? Scott will talk to Larry about #3 and 4
4) I think it is Wissco’s responsibility
to start up the lawn irrigation system that is new that serves Memorial’s
property is that correct? If so when will that be done?
Action Items
1.
Colfax and MLK steps.-Roger will look at
this and let me know.
2.
Pave Drain low- we talk about it after
next week’s meeting
3.
Majority Builders Sidewalk work- move
forward as planed
4.
Chase tower. Reith Riley will price the
wok to be done on an accelerated option to try to complete by June 1 if they receive it by the first week
of May.
5.
Landscape work – is starting up this week
6.
Trash can locations- Mike Divita will look
into this
7.
Cycle track Markings- waiting on pricing
from Airmarking should find out Monday.
8.
Sign for Marion Street- a new sign for
Marion will need to be installed
9.
When will the Rail Road signs be installed?
They are in and will be installed ASAP
10.
The Change orders for the Guardrail and
thermos detection will need to address the delivery time with and additional
two weeks for installation’s
Reith Riley Construction
Concerns/Questions
1.
Century center Parking- this issue seems to be
resolved
2.
Pending Changes- No other changes are in the
works
City
Concerns/Questions:
When will the lighting under the bridges be done. The lights
are expected to be delivered in the next week.
Who switched the handicap parking sign to 2 hour parking, no
one knows.
Next weekly progress 4-28-17