Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Land scape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Cloudy Rain at 2:00pm
Hi 78 Lo 58

A meeting over the Pave Drain was held today. Al from Pave Drain will Communicate with Rich from structure Point and Mike  from Lawson Fisher and have a recommendation to Reith Riley which will then present it to the City.

Reith Riley had a 9 man Concrete crew pouring the sidewalk on the west side of Saint Joe Street from Wayne to Jefferson.

Reith Riley had a 3 man prep crew working on the west side of Saint Joe from Wayne to Jefferson out ahead of the concrete crew. They then went to the North east and North west corners of Navarre and Michigan. Once that was completed they went down to division A and worked on punch list items.

Reith Riley had a 6 man brick crew working on the North West Corner of Wayne and Main and the North East corner of Wayne and Main.

Pemberton Davis has a 7 man crew working at the intersection of Colfax and Saint Joe Street on the South east and South West corners. They are also working on Saint Joe street on the street lights on the west side from Jefferson to Wayne street. 

Wisco has a 4 man crew working on the irrigation on the east side of Saint Joe from Jefferson to Wayne.

Indiana Earth  not on site 

Airmarking had a 3 man crew working on Main Street at Wayne Jefferson and Colfax doing the cross walk. done at 2 due to the rain