Monday, April 17, 2017

4-17-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Land scape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny 
Hi 72 Lo 48

Reith rily had a Nine man concrete crew working on the South West Corner of LaSalle and Saint Joe street. They then went to the North West corner of LaSalle and saint Joe Street. Then moved to the South East corner of LaSalle and Main.

Reith Riley had a 3 man prep crew working on the intersection of Saint Joe and Jefferson on the North East Corner and then the South East corner.

Reith Riley had a 3 man brick crew working on the South east corner of Main and Washington in front of the TCU building.

Indiana earth had a 4 man crew working on the the sidewalk removals on the west side of Saint Joe from Wayne to Jefferson.

State Barricade came in and closed south Bound Saint Joe Street from Wayne to Jefferson. They started at 7:30 AM and opened it back up at 4:30 pm

Wiscco had a 4 man crew working on the sprinkler system on Saint Joe from Washington to Wayne street on the east side of the raod.

Pemberton Davis had a 7 man crew working on pulling wire from Navarre to Bartlett on the east side of the. They then went to north of Bartlett to the River on the east side of the road. They also worked on some conduit on the South east corner of Colfax and Saint Joe for the walk wait, They also worked on the power supply at Monroe and Michigan. Then worked on the conduit for the lighting on the west side of Saint Joe from Jefferson to Wayne Street.