Thursday, April 20, 2017

4-20-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy Rain done by 7:30 PM Cloudy Rain at 2:00 pm
Hi 78 Lo 58

Reith Riley had a 9 man concrete crew working on the North West and South West corner of Saint Joe and Wayne Street. They then moved to Navarre and Michigan and started forming they got rained out at 2 pm.

Reith Riley had a 3 man prep crew working on the South East corner of Saint Joe and Jefferson Street. prepping for Sidewalk. They then left the job site at around 10:00 am

Reith Riley had a 6 man brick crew working on the South East corner of Main and Washington in front of the TCU building. 

Wisco had a 4 man crew working on the east side of Saint Joe Street between Wayne and Jefferson working on the Irrigation.

Pemberton Davis had a 7 man crew working on the intersection of Wayne and Saint Joe on the South West and South East corners. They also worked on the North East and North West corners of Navarre and Michigan

Indiana Earth was not on site today.

Airmarking was not on site today due to the morning rain and afternoon rain.