Monday, April 24, 2017

4-24-17

Controlling Operation Bartlett: Traffic Markings
Controlling Operation Marion: Landscape work
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 73 Lo 44

Reith Riley had a 8 man concrete crew pouring the South West corner of Colfax and MLK. They then poured the North west corner of Monroe and MLK

Reith Riley had a 3 man prep crew show up around noon and work on the South east and South west corners of Western and MLK

Reith Riley had 6 men working on brick 3 cutting brick at the North West corner of Main and Wayne. The second crew worked on placing sand on various locations on Main Street.

Wisco had a 4 man crew working on MLK from Washington to Wayne on the east side of the road.

Airmarking had a 3 man crew working on the crosswalks on main street from Madison to Western.

Indiana Earth worked cleaning up the parking area north of McDonald's.

Pemberton Davis has a 7 man crew working on changing out the traffic controller at the intersection of Wayne and MLK. They also relocated the Mast arm in the North west corner and placed the 2 light poles on the south west and south east corners. They placed the walk waits at all four corners. They have a 2 man crew working on painting strain poles at Main and Colfax. 