The walk through was held for Main Street and MLK from LaSalle to Western.
Pemberton Davis had a 5 man crew working at the intersection of Wanye and Main.
Pemberton Davis had a 2 man crew painting at Monroe and Main.
Slussers had a 4 man crew working on Sodding and placing edging in various areas.
Walk Through for Downtown Two-way
Conversion
Main St.
·
Parking spots striped on the south side of
LaSalle, just east of Main St.
·
Temporary straight arrow removed on southbound
Main St. at LaSalle.
·
Concrete needs poured at SE corner of LaSalle
and Main St. strain pole base.
·
River rock needs to be added next to sidewalk on
the east side of Main St. behind the Morris.
·
The no parking sign on Washington near Lafayette
needs changed/ moved to be at the end of the stall.
·
All banner arms need to be moved to be away from
traffic of light poles and removed from all poles in intersection bump-outs.
·
Trees need to be secured better.
·
Fill in all paver joints with more sand wherever
needed.
·
Sweep sidewalk, cycle track and road.
·
Finish any striping left.
·
Grout under mast arms.
·
Northwest corner of Main and Western is missing
a trash can.
·
Grout under Mast Arms were needed.
·
Check all Walk/Waits some not working
·
Clean Push ped North east corner
·
Need stone behind sidewalk at Morris
drive(landscape rocks/2’s)
·
No right on red signs
MLK Blvd.
·
Take down informational two-way conversion signs.
·
Duct taped plant needs replaced on east side of
MLK north of Wayne.
·
Wire sticking up in sod between Century Center
parking lot and sidewalk, south of Jefferson.
·
Dead sod in front of the Century Center.
·
Brick paver band on southeast corner of
Washington and MLK needs adjusted.
·
Cut off excess concrete on cabinet base and pour
concrete around cabinets on southeast corner of Washington and MLK.
·
Pour concrete around Cabinet and Tesco at South
East corner of Jefferson and MLK
·
Place sod behind cabinets Jefferson and MLK
South East quad
·
South west Corner Jefferson MLK Cut and Cap line
lower
·
Saw cut groove in sidewalk between Washington
and Jefferson on MLK
·
Move bike sign south of Washington farther south
to next concrete pad
·
Water Fountain
·
Remove INDOT mile marker just north of
washington
·
Fill in Concrete around hand hole South East
corner Jefferson and MLK
·
Cut off pipe at northeast corner of Washington
and MLK.
·
Order spare snow markers.
·
Paint top of curb at Colfax and MLK south east
and North East.
·
Sweep at century center parking lot
·
Remove no parking signs on School building light
poles
·
Wisco pipe North east corner Washington and MLK
·
Double tree irrigation
·
Covers for back flow
·
Stain man hole bike path brick areas
·
Straighten Light heads that have spun
·
Calk cabinet bottoms
·
Sod LaSalle east of MLK before bridge small area
·
Yellow thermos over patch between Colfax and
LaSalle
·
West bound LaSalle white stripping between
Williams and Lafayette
·
Yellow curb top at LaSalle and Main South East
corner
·
Pull all Dead Trees and replace this fall
·
Concrete sidewalk South east corner of Sample
and main
·
Concrete Service walk on Michigan South of
Madison west side north parking area
·
Concrete sidewalk slab remove west side of
Michigan north of LaSalle