Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 82 Lo 48
Reith Riley had not on site today.
Pemberton Davis had a 2 man crew painting Mast Arms at South and Michigan.
Pemberton Davis had a 4 man crew working on Main and LaSalle and MLK and Western.
Wisco had a 4 man crew working on fixing irrigation.
Meeting Agenda
Reith Riley had not on site today.
Pemberton Davis had a 2 man crew painting Mast Arms at South and Michigan.
Pemberton Davis had a 4 man crew working on Main and LaSalle and MLK and Western.
Wisco had a 4 man crew working on fixing irrigation.
Meeting With:
|
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1. Rieth Riley:
Wisco will be on site finishing repair work on irrigation they should be done
in 2 weeks. Airmarking has miscellaneous epoxy and thermos work to do once the
pave drain is resolved. Slussers will be in next week and try to finish punch
list items.
2. Pemberton Davis: will be
working at Lafayette and LaSalle Monday and Tuesday. They will finish any
wiring neede done. They will work on the Cabinets that need rewired.
Utility Relocation Issues:
AEP:
1.
Michigan and Indian
2.
Poles on Marion east of Michigan: AEP is working
on this with AT&T
Robert Henry:
Metronet:
Transpo: No Questions
311
DTSB : Asked about the left
turn at Monroe and Michigan heading east.
Utilities Q/A
INDOT: Questions:
Stakeholder Questions:
Memorial Hospital
Larry will wait a couple more weeks before placing locks on
backflow preventers.
I will walk the north section next week to review what needs
fixed from the punch list.
Action Items
1.
Pave drain: I will call and talk to Steve
Benzick from INDOT to discuss the repair limitations as to what is acceptable
and what is not. Rieth Riley will have a crew available possibly the 19th
or the 26th to get the work done. Once the fix is agreed upon.
2.
Chase Tower: has moved the barrio and now
pemberton Davis can get in and do the work on that corner to get the signal
operational.
3.
Irrigation, Double Tree, Burger King: Wisco
should have this work done in2 weeks.
4.
Tree grate and Brick Storage 7 tree grates will
need to be stored and 65 pallets of brick once the City figures out where they
want them placed.
5.
Traffic accidents: that have no insurance will
be paid through the contract, the city insurance has too big of a deductible.
6.
Parking stalls Wayne Street Michigan to Main
utility work is completed in this area and can now be striped
7. Weekly
Progress meetings: keep having them until the pave drain is resolved.
Reith Riley Construction
Concerns/Questions
City
Concerns/Questions
The City would like to know if white bike emblems can be
added to the green cross walk areas.
June 21st Main Street will be closed from 10:00am
to 12:00 pm to dedicate the MLK Statue at the Leighton Plaza
The tentative date for the ribbon cutting will be June 16 at
the Century Center.
I need to look into the stop sign installed at the corner of
MLK and Wayne street North east.