Wednesday, June 7, 2017

6-7-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 74 Lo 58

The walk through was held for Main Street and MLK from LaSalle to Western.

Pemberton Davis had a 5 man crew working at the intersection of Wanye and Main.

Pemberton Davis had a 2 man crew painting at Monroe and Main.

Slussers had a 4 man crew working on Sodding and placing edging in various areas.



Walk Through for Downtown Two-way Conversion
Main St.
·         Parking spots striped on the south side of LaSalle, just east of Main St.
·         Temporary straight arrow removed on southbound Main St. at LaSalle.
·         Concrete needs poured at SE corner of LaSalle and Main St. strain pole base.
·         River rock needs to be added next to sidewalk on the east side of Main St. behind the Morris.
·         The no parking sign on Washington near Lafayette needs changed/ moved to be at the end of the stall.
·         All banner arms need to be moved to be away from traffic of light poles and removed from all poles in intersection bump-outs.
·         Trees need to be secured better.
·         Fill in all paver joints with more sand wherever needed.
·         Sweep sidewalk, cycle track and road.
·         Finish any striping left.
·         Grout under mast arms.
·         Northwest corner of Main and Western is missing a trash can.
·         Grout under Mast Arms were needed.
·         Check all Walk/Waits some not working
·         Clean Push ped North east corner
·         Need stone behind sidewalk at Morris drive(landscape rocks/2’s)
·         No right on red signs
MLK Blvd.
·         Take down informational two-way conversion signs.
·         Duct taped plant needs replaced on east side of MLK north of Wayne.
·         Wire sticking up in sod between Century Center parking lot and sidewalk, south of Jefferson.
·         Dead sod in front of the Century Center.
·         Brick paver band on southeast corner of Washington and MLK needs adjusted.
·         Cut off excess concrete on cabinet base and pour concrete around cabinets on southeast corner of Washington and MLK.
·         Pour concrete around Cabinet and Tesco at South East corner of Jefferson and MLK
·         Place sod behind cabinets Jefferson and MLK South East quad
·         South west Corner Jefferson MLK Cut and Cap line lower
·         Saw cut groove in sidewalk between Washington and Jefferson on MLK
·         Move bike sign south of Washington farther south to next concrete pad
·         Water Fountain
·         Remove INDOT mile marker just north of washington
·         Fill in Concrete around hand hole South East corner Jefferson and MLK
·         Cut off pipe at northeast corner of Washington and MLK.
·         Order spare snow markers.
·         Paint top of curb at Colfax and MLK south east and North East.
·         Sweep at century center parking lot
·         Remove no parking signs on School building light poles
·         Wisco pipe North east corner Washington and MLK
·         Double tree irrigation
·         Covers for back flow
·         Stain man hole bike path brick areas
·         Straighten Light heads that have spun
·         Calk cabinet bottoms
·         Sod LaSalle east of MLK before bridge small area
·         Yellow thermos over patch between Colfax and LaSalle
·         West bound LaSalle white stripping between Williams and Lafayette
·         Yellow curb top at LaSalle and Main South East corner
·         Pull all Dead Trees and replace this fall
·         Concrete sidewalk South east corner of Sample and main
·         Concrete Service walk on Michigan South of Madison west side north parking area
·         Concrete sidewalk slab remove west side of Michigan north of LaSalle