Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 90 Lo 70
Pemberton Davis had a 6 man crew working on the intersection of Lafayette and LaSalle. They then worked at putting up signs in Various locations.
Pemberton Davis had a 2 man crew working on painting poles this work is now complete.
Air Marking had a 2 man crew placing bike emblems on the green cross walks on MLK and Main Street.
Wisco had a 4 man crew working on irrigation at the double tree and various locations.
Nelson from Slussers stopped and went over their remaining work.
Pemberton Davis had a 6 man crew working on the intersection of Lafayette and LaSalle. They then worked at putting up signs in Various locations.
Pemberton Davis had a 2 man crew working on painting poles this work is now complete.
Air Marking had a 2 man crew placing bike emblems on the green cross walks on MLK and Main Street.
Wisco had a 4 man crew working on irrigation at the double tree and various locations.
Nelson from Slussers stopped and went over their remaining work.