Friday, June 16, 2017

6-16-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy  PM Mostly Sunny 
Hi 88 Lo 68

Pemberton Davis had a 6 man crew working on the Washington and Main intersection. They also worked on the intersection of Main and Monroe pouring back some side walk.

Rieth Rily had a 7 man crew doing punch list work on Main and MLK 

Mayor had his ribbon cutting speech at 11 am.

Thursday, June 15, 2017

6-15-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy Rain  PM Mostly Sunny 
Hi 88 Lo 68

Reith Riley had a 5 man concrete crew finish the concrete punch list items.

Reith Riley had a 5 man crew working on clean up and punch list items, They also set the planters at the corner of Colfax and MLK 

AirMarking had a 3 man crew placing epoxy paint where needed.

Pemberton Davis had a 5 man crew working at Main and Washinton on the North West Corner 

Pemberton Davis also worked on the thermo detection at Colfax. Washington and MLK. They also worked on Monroe and Main cabinet fine tooning.

Wednesday, June 14, 2017

6-14-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny   PM Mostly Sunny 
Hi 90 Lo 70

Pemberton Davis had a 7 man crew working at the intersection of Main and Monroe placing a had hole and new Cabinet.

Slussers had a 5 man crew placing sod and working on punch list items.

Wisco had a 4 man crew working on irrigation issues.

Airmarking had a 2 man detail crew working punch list items mainly parking stalls on the side streets.

Reith Riley had a 5 man crew pouring the remaining sidewalk/ punch list items.


Tuesday, June 13, 2017

6-13-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny   PM Rain 
Hi 90 Lo 70

All work suspended when the rain started at 1:00 pm.

Pemberton Davis had a 1 man removing and adjusting Banner arms and street lights.

Pemberton Davis had 1 man grouting under Mast arms.

Pemberton Davis had 5 man crew working at the intersection of Monroe and Main placing a Hand Hole.

Wisco had a 4 man crew working at various location fixing irrigation.

Slussers had a 4 man crew working on punch list items dirt in planters, mulch river rock.

Rieth Riley finished tiling the building at Main and Western, They then worked on pouring miscellaneous pieces of concrete on the punch list.

Monday, June 12, 2017

6-12-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny   PM Mostly Sunny 
Hi 90 Lo 70

Pemberton Davis had a 6 man crew working on the intersection of Lafayette and LaSalle. They then worked at putting up signs in Various locations. 

Pemberton Davis had a 2 man crew working on painting poles this work is now complete.

Air Marking had a 2 man crew placing bike emblems on the green cross walks on MLK and Main Street.

Wisco had a 4 man crew working on irrigation at the double tree and various locations.

Nelson from Slussers stopped and went over their remaining work.

6-9-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy    PM Mostly Sunny 
Hi 84 Lo 52

Reith Riley had a 3 man crew working on replacing the tile on the building at Western and Main

Pemberton Davis had a 2 man crew painting Mast Arms at Monroe and Main Street and Navarre and Michigan.

Pemberton Davis had a 2 man crew working at LaSalle and Lafayette pushing conduit under the road.

Pemberton Davis had a man working on the cameras at Colfax and Michigan.

Wisco had a 4 man crew working on irrigation throughtout the project.


Meeting Minutes
Meeting With:
Rieth Riley & City of South Bend


Meeting Date:
6-9-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Rieth Riley –will be in Monday to finish concrete work, Wednesday and Thursday to do clean up. Slusser will be in Tuesday to work on punch list items. Wisco will continue to work on the sprinklers

2.       Pemberton Davis- will have the poles painted by the end of today and finish the touch up work next week. Lafayette and LaSalle done by Monday. MLK is done work on Main Street loops and cross walks next week.

Utility Relocation Issues:
AEP: 
1.       Michigan and Indian
2.       Poles on Marion east of Michigan
Robert Henry:

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: Memorial Hospital
Action Items  

1. Pave drain-Scheduled to meet with Indot on Wednesday on hold until then.
2. Chase Tower-Work on the traffic signal needs done
3. Irrigation- Josh will get me the bill for the repair work between LaSalle and Wayne
4. Tree grate and Brick Storage- Tree grates will go to Calvert Street, street department yard, bricks will stay at main and South street lot
5. Traffic accidents (need cost) Josh will get the cost for the noninsured ones.
6. Fiber Optic splicing when is it going to be done.
               
Reith Riley Construction Concerns/Questions

City Concerns/Questions
No Right Turn Signs- Roger is looking into MLK area and will have to bounce Main Street off INDOT.

Crosswalk at Century Center needs to be cleaned for the Ribbon Cutting

Pedestrian Emblems at cross walks I need to send an email to Jitin to see if he wants them.
                               





Thursday, June 8, 2017

6-8-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 78 Lo 52

Reith Riley had a 3 man crew work on the building at western and Main fixing the tile.

Pemberton Davis had a 4 man crew working at Wayne and MLK replacing the Controller Cabinet. they then went to Lafayette and LaSalle and hung the 5 section heads.

Pemberton Davis had a 2 man crew painting the Mast Arms at Monroe and Main Street.

There was a sink hole that developed on Main Street south of Western in the turn lane that the sewer department repaired.

Wisco had a 5 man crew working on irrigation around the hospital.