Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny    PM Mostly Sunny 
Hi 74 Lo 52

Reith riley had no one on site today.

Pemberton Davis had a 5 man crew remove the receps by the hospital. they worked on Western and main hooking up the loops.

Pemberton Davis had a 2 man  crew painting the poles at Monroe and MLK.

No other work took p[lace today  