Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Mostly Sunny
Hi 74 Lo 52
Reith riley had no one on site today.
Pemberton Davis had a 5 man crew remove the receps by the hospital. they worked on Western and main hooking up the loops.
Pemberton Davis had a 2 man crew painting the poles at Monroe and MLK.
No other work took p[lace today
Reith riley had no one on site today.
Pemberton Davis had a 5 man crew remove the receps by the hospital. they worked on Western and main hooking up the loops.
Pemberton Davis had a 2 man crew painting the poles at Monroe and MLK.
No other work took p[lace today