6-9-17

Controlling Operation Bartlett: Punch List
Controlling Operation Marion: Punch List
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy    PM Mostly Sunny 
Hi 84 Lo 52

Reith Riley had a 3 man crew working on replacing the tile on the building at Western and Main

Pemberton Davis had a 2 man crew painting Mast Arms at Monroe and Main Street and Navarre and Michigan.

Pemberton Davis had a 2 man crew working at LaSalle and Lafayette pushing conduit under the road.

Pemberton Davis had a man working on the cameras at Colfax and Michigan.

Wisco had a 4 man crew working on irrigation throughtout the project.


Meeting Minutes
Meeting With:
Rieth Riley & City of South Bend


Meeting Date:
6-9-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Rieth Riley –will be in Monday to finish concrete work, Wednesday and Thursday to do clean up. Slusser will be in Tuesday to work on punch list items. Wisco will continue to work on the sprinklers

2.       Pemberton Davis- will have the poles painted by the end of today and finish the touch up work next week. Lafayette and LaSalle done by Monday. MLK is done work on Main Street loops and cross walks next week.

Utility Relocation Issues:
AEP: 
1.       Michigan and Indian
2.       Poles on Marion east of Michigan
Robert Henry:

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: Memorial Hospital
Action Items  

1. Pave drain-Scheduled to meet with Indot on Wednesday on hold until then.
2. Chase Tower-Work on the traffic signal needs done
3. Irrigation- Josh will get me the bill for the repair work between LaSalle and Wayne
4. Tree grate and Brick Storage- Tree grates will go to Calvert Street, street department yard, bricks will stay at main and South street lot
5. Traffic accidents (need cost) Josh will get the cost for the noninsured ones.
6. Fiber Optic splicing when is it going to be done.
               
Reith Riley Construction Concerns/Questions

City Concerns/Questions
No Right Turn Signs- Roger is looking into MLK area and will have to bounce Main Street off INDOT.

Crosswalk at Century Center needs to be cleaned for the Ribbon Cutting

Pedestrian Emblems at cross walks I need to send an email to Jitin to see if he wants them.
                               