Tuesday, February 28, 2017

2-28-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy rain PM Cloudy rain
Hi 59 Lo 45

Pemberton Davis worked on setting street lights from Navarre to bartlett on the east side of Michigan. They also worked on moving the controller cabinet at the intersection of Wayne and Main.

Tuesday 2-28-17 
    Michigan St. Lighting; installed light poles on east side between Navarre and Bartlett. 
    Main St. Lighting; installed light poles in several places 1@ Washington, 2@ Wayne, spliced all poles. 
    Main and Wayne; relocated controller cabinet to new foundation and removed temp signal cable, rewired cabinet. AEP removed existing power feed to controller cabinet before it was moved. 

No other work took place today.

Monday, February 27, 2017

2-27-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM sunny PM sunny
Hi 45 Lo 31

Pemberton Davis worked on setting street lights from Navarre to Just north of Bartlett on the east side of Michigan. They also reset the street lights on the west side of the Bartlett Round about.

for Monday 2-27-17

     Bartlett roundabout; removed temp lights and installed 23' light poles and fixtures. 

Robert Henery worked on the south side of Western ave just west of Michigan. They also had a crew working in the drive to the water department on Bartleet Street just east of Michigan.

No Other work took place today.

Friday, February 24, 2017

2-24-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy PM cloudy rain
Hi 62 Lo 42

Pemberton Davis worked on setting the walk waits and pulling wire at the intersection of Wayne and Main they had a 6 man crew.

Friday 2-24-17
    Main St. Lighting; splicing poles. 
    Main St. ; set 12' pedestal poles. 1@ Washington, 1@ Jefferson, 2@ Wayne. Set pedestrian signals/push buttons 2/1 @ Washington (SW), 2/1 @ Jefferson (SW), 4/2 @ Wayne (NW)&(SW). 

    Main and Wayne; installed signal cable around intersection. 


Slussers was on site to straighten trees up.

No other work was done today.

Thursday, February 23, 2017

2-23-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Foggy PM Mostly Sunny
Hi 62 Lo 42

Pemberton Davis worked on placing push ped foundations and walk wait foundations at Wayne and Main and at Washington and Main. They had a second crew working on splicing street lights on Michigan from LaSalle north to Marion. They then went and spliced street lights on the east side of Main Street from Wayne to Jefferson. 

Thursday 2-23-17
    Main St.; installed lighting and A-foundations. L- 1@ Washington, 2@ Wayne 
A- 1@ Washington, 1@ Jefferson, and 2@ Wayne. 
    MLK lighting; splicing poles. 

I contacted Slussers get get the trees straightened up on Main Street.

No other work took place today.

Wednesday, February 22, 2017

2-22-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy PM Cloudy
Hi 62 Lo 42

Pemberton Davis got the walk waits at Jefferson and Main Street working. They also worked on the walk waits on  Washington and Main. They also had a crew working on pulling wire on the lights north of LaSalle on Main and on Michigan.

Wednesday 2-22
    MLK lighting; pulling in more wire and splicing poles. 
    Main St. ; installed more handicap signs. 
    Main St. and Washington; removed existing mast arm, Signal heads, pedestrian signal heads,and signs. Relocated heads to new mast arm and controller cabinet to new foundation. Rewired cabinet and turned on signals and pedestrian signals. 

    Main and Jefferson; Spliced cabinet and turned on pedestrian signals. 


No other work took place today

2-21-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Rain PM Cloudy Rain
Hi 62 Lo 38

Pemberton Davis had a crew working on pulling wire on the street lights on Main Street and Michigan from LaSalle to Marion. the crew went home after 4 hours due to the rain.

Tuesday 2-21-17
    MLK lighting; pulled in more #4 and #6 lighting cable and spliced poles. 
    Main St.; set handicap signs. 

Then we were rained out. 


No other work took place today.

Monday, February 20, 2017

2-20-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 62 Lo 38

Pemberton Davis worked on setting the last of the street  lights North of LaSalle on Michigan and on Main they are going to work on pulling wire to the street lights.  

From Pemberton: 
Monday 2-20-17
   MLK and LaSalle; set light poles and conduit runs on north side. 
   MLK lighting; installing lightning cable south of LaSalle. 
   Main St. Lighting; set light pole at church. 
   Bartlett St.; reset signs at St. Joseph St. 

Friday, February 17, 2017

2-17-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 50 Lo 30

Pemberton Davis is working on the walk/Waits at the corner of Jefferson,Washington and Wayne on Main Street. 

State Barricade is removing the Message Boards on Colfax and at the intersection of Saint Joe and South Street.

Phil @ Pemberton; "Main St. Lighting; spliced poles on east side north of Wayne St.   
Main St. Signals ; installed pedestrian signals and push buttons at several intersections. Washington, Jefferson,and Wayne St.   
Main and LaSalle; set a 12' pedestal pole on SE corner."

Thursday, February 16, 2017

2-16-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Sunny PM Mostly Sunny   
Hi 39 Lo 30

Pemberton Davis worked on the street lights on Main Street from Marion to LaSalle. They also worked on the signage in the same area along with the bollard lighting. 

No other work took place.



Phil @ Pemberton; "MLK Blvd lightning; dig and poured base north of LaSalle. 
Main St. Lighting; removed existing foundation in front of church, dug and poured new foundation just south of that one. 
Main and LaSalle; dug and poured an pedestal foundation on SE corner." 

Wednesday, February 15, 2017

2-15-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy light snow PM partly Sunny   
Hi 38 Lo 30

Pemberton Davis worked on setting street light poles on Main Street from Marion to LaSalle. They also worked on placing signs on  Main Street and Michigan from Bartlett to LaSalle.

No other work took place today.

Phil @ Pemberton; "Main St. Lighting; installed light poles north of LaSalle. 
MLK Blvd signs ; set signs north of LaSalle to Navarre. Removed several signs as well." 

Tuesday, February 14, 2017

2-14-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 45 Lo 30

Pemberton Davis put up street lights on Michigan from LaSalle to Marion and then moved to Main street and started working on Street lights from Marion to main. 

Reith Riley worked on Snow plow markers on Saint Joe street. 

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; set light poles north of La Salle to roundabout. 
Main St. Signals ; set 12' pedestal poles at several locations, NE- Washington, NE- Jefferson, NE- Wayne."

Monday, February 13, 2017

2-13-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny   
Hi 42 Lo 28

Pemberton Davis worked on placing  street lights on the east and west side of Saint Joe between Colfax and LaSalle. They also worked on the walk waits for Bronson and Main. They also worked on the street lights North of LaSalle on Michigan.

Reith Riley worked on the last of the snow plow markers on saint Joe street.

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; set light poles south of La Salle and installed conduit runs to foundations."

Friday, February 10, 2017

2-10-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy PM Cloudy   
Hi 38 Lo 18

Pemberton Davis worked on pouring foundations for street lights on the east and west side of Saint Joe between Colfax and LaSalle. They also worked on the walk waits for Bronson and Main.

No other work took place today.

Phil @ Pemberton; "MLK and La Salle ; lighting foundations on south side of intersection. Had to hand dig due to utilities in area."




Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
2-10-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1. Reith Riley- will continue to work on the snowplow markers as weather permits
                                2. Pemberton Davis- Pemberton Davis will work on streetlights north of LaSalle on Main and Michigan. They will also work on signs no parking/chevrons on the roundabouts/Marmain loading zone. 
Utility Relocation Issues:
AEP: 
1.       Power at Wayne and Main- will get next week
2.       Power at Colfax and Saint Joe Both meters-will get next week
3.       Jefferson and saint Joe along with Washington and Saint Joe- next week
Robert Henry:
1.       Vault at Main and LaSalle- need a work order from AEP and they will get it done as quick as possible          
Metronet: 
1.       WIFI on Saint Joe and Main Pemberton Davis Gave a list to MetroNet. Metronet will work on the intersections that are done, but the Wi-Fi will stay down until all locations are completed.
2.       Metronet will be running a feed to the LaSalle grill on main Street and a side walk panel is cracked they wanted to bring to the attention before they       
NPSCO:
                                1 Work left on Michigan Street- will get with Robert Henry and the City to keep thing moving.
Utilities Q/A

INDOT: Questions:
The permit for this project expires in March and needs to be extended; Roger will take care of that.   

Stakeholder Questions: Larry asked about the crosswalk lights at Bartlett, tanner expects the parts in next week and hoping to have it fully functional the following week. Don’t forget the light pole at Bartlett and Main. When will all the lights from Marion North be done, end of February.


Thursday, February 9, 2017

2-9-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy light snow PM Cloudy light Snow  
Hi 22 Lo 18

Pemberton Davis worked on street lighting on the east and west side of Saint Joe. They assembled and set the lights from Jefferson to Colfax on Saint Joe and the 2 just north of Jefferson on the east side of Saint Joe. 

No Other work took place today. 

Phil @ Pemberton; "MLK Blvd lighting; installed lights on foundations north of Jefferson to Colfax. 
MLK and Washington; removed pedestrian signals and poles around the intersection." 

Wednesday, February 8, 2017

2-8-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy light Snow  
Hi 34 Lo 28

Pemberton Davis worked on pulling wire and setting lights on Saint Joe Street from Colfax to Jefferson on the east and west side of the street.

No other work took place today.

Phil @ Pemberton; "MLK Blvd lighting; installed conduit in several locations north of Jefferson to Colfax. 
MLK and LaSalle ; removed pedestrian foundation on SW corner. 
MLK and Colfax; removed pedestrian pole and foundation."

Tuesday, February 7, 2017

2-7-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Rain  PM Cloudy Rain  
Hi 56 Lo 48

No work today due to the heavy Rain.


Monday, February 6, 2017

2-6-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Sunny  PM Partly Cloudy  
Hi 45 Lo 28

Pemberton Davis worked on the street lighting on Saint Joe Street from LaSalle to Colfax on the East side of the road they finished pouring the foundations. They also worked on getting the actuation working on South Street and Michigan that started working around 10:45 AM.

Reith Riley worked on setting the snow plow markers on Saint Joe Street.

No other work took place today.

Phil @ Pemberton; "Michigan and South St. ; TCC programmed cameras all working fine. 
Main and South St. ; set more pedestrian signals no SE corner. Also removed existing. 
MLK Blvd lighting; installing light base between Jefferson and Colfax."


Friday, February 3, 2017

2-3-17


Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy windy cold  PM Cloudy  
Hi 26 Lo 16

Pemberton Davis continued to work at the intersection of Michigan and South Street. They hung the heads on the South Bound Mast arms and finished wiring the intersection. The City then inspected the work and the signal was activated around 3:30. 

Phil @ Pemberton; "Michigan and South St. ; set SB signal heads, had to cover heads. Spliced poles and cabinet. Removed all bags and turned signals on at 3:15 pm. 
Main and South St. ; removed existing pedestrian signals and installed new pedestrian signals and push buttons."

2-2-17


Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy  PM Mostly Sunny
Hi 27 Lo 16

Pemberton Davis had a 7 man crew on site. They set the Tesco Cabinet and they moved the Controller Cabinet at the intersection of South an Michigan. They also strung new wire to up the strain poles. 

AEP showed up and ran power to the new Tesco that was completed around 1:00 PM. 

No other work took place today.

Phil @ Pemberton; "Michigan and South St. ; set pedestrian poles around intersection along with pedestrian signals and push buttons. Installed signal cable around the intersection and in SB mast arm. Set new signal cabinet and Tesco. Installed 3" and 1" conduit at Tesco cabinet."