Friday, February 10, 2017

2-10-17

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Partly Cloudy PM Cloudy   
Hi 38 Lo 18

Pemberton Davis worked on pouring foundations for street lights on the east and west side of Saint Joe between Colfax and LaSalle. They also worked on the walk waits for Bronson and Main.

No other work took place today.

Phil @ Pemberton; "MLK and La Salle ; lighting foundations on south side of intersection. Had to hand dig due to utilities in area."




Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
2-10-17


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1. Reith Riley- will continue to work on the snowplow markers as weather permits
                                2. Pemberton Davis- Pemberton Davis will work on streetlights north of LaSalle on Main and Michigan. They will also work on signs no parking/chevrons on the roundabouts/Marmain loading zone. 
Utility Relocation Issues:
AEP: 
1.       Power at Wayne and Main- will get next week
2.       Power at Colfax and Saint Joe Both meters-will get next week
3.       Jefferson and saint Joe along with Washington and Saint Joe- next week
Robert Henry:
1.       Vault at Main and LaSalle- need a work order from AEP and they will get it done as quick as possible          
Metronet: 
1.       WIFI on Saint Joe and Main Pemberton Davis Gave a list to MetroNet. Metronet will work on the intersections that are done, but the Wi-Fi will stay down until all locations are completed.
2.       Metronet will be running a feed to the LaSalle grill on main Street and a side walk panel is cracked they wanted to bring to the attention before they       
NPSCO:
                                1 Work left on Michigan Street- will get with Robert Henry and the City to keep thing moving.
Utilities Q/A

INDOT: Questions:
The permit for this project expires in March and needs to be extended; Roger will take care of that.   

Stakeholder Questions: Larry asked about the crosswalk lights at Bartlett, tanner expects the parts in next week and hoping to have it fully functional the following week. Don’t forget the light pole at Bartlett and Main. When will all the lights from Marion North be done, end of February.