Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy PM cloudy rain
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM cloudy PM cloudy rain
Hi 62 Lo 42
Pemberton Davis worked on setting the walk waits and pulling wire at the intersection of Wayne and Main they had a 6 man crew.
Friday 2-24-17
Main St. Lighting; splicing poles.
Main St. ; set 12' pedestal poles. 1@ Washington, 1@ Jefferson, 2@ Wayne. Set pedestrian signals/push buttons 2/1 @ Washington (SW), 2/1 @ Jefferson (SW), 4/2 @ Wayne (NW)&(SW).
Main and Wayne; installed signal cable around intersection.
Slussers was on site to straighten trees up.
No other work was done today.
Pemberton Davis worked on setting the walk waits and pulling wire at the intersection of Wayne and Main they had a 6 man crew.
Friday 2-24-17
Main St. Lighting; splicing poles.
Main St. ; set 12' pedestal poles. 1@ Washington, 1@ Jefferson, 2@ Wayne. Set pedestrian signals/push buttons 2/1 @ Washington (SW), 2/1 @ Jefferson (SW), 4/2 @ Wayne (NW)&(SW).
Main and Wayne; installed signal cable around intersection.
Slussers was on site to straighten trees up.
No other work was done today.