Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Partly Cloudy PM Partly Cloudy
Hi 79 Lo 65
Rieth-Riley had a concrete crew that poured curb ramps at the northwest and southwest corners of the intersection of Main and South. They also poured the curb ramp at the southwest corner of Main and Bronson.
Ziolkowski continued forming for the concrete walls in the center of the Marian roundabout.
Pemberton Davis worked on lighting at the Bartlett roundabout.
The weekly progress meeting with utilities was held in the morning. Meeting minutes are below.
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
·
Traffic
closure update:
Washington was opened this morning (7/29). Removals are
going to continue on the East side of Main moving south. The switch on Main
between South and Bronson will be happening on Monday (8/1). Late next week the
switch on Main between LaSalle and Madison will happen along with Michigan at
Madison and Marion. Reith Riley is not planning on doing any paving until the
week of 8/8 but will continue to patch Bronson and Main today (7/29). Striping
will begin down in Division A soon with all white lines being painted along
with the left turn lane. Main will also have striping done but will continue
with same traffic flow to Barbie. Next Friday (8/5) opening Michigan northbound
with extensive barricades. Roger, Scott and Myron agreed to schedule a meeting
with Xavier school of excellence (hopefully for 8/3) to discuss the traffic
changes, hard dates for when things are changing, and the fact that the city is
not going to be doing any work on the approach.
Utility Relocation Issues:
AEP: Complete
Robert Henry: They still have work just North of South Street on
Main Street, approx. 2 weeks to have work completed. Will move further south
after the traffic switch. Will also be addressing the complaint about lose
asphalt on Main.
NIPSCO/InfraSource: Patching on Lafayette is finished. Need
to contact Brian to follow up on replacing curb. Toy would like to schedule a
meeting with Brian to go out and look at the curb.
Comcast: Still need to get a
line across at Marion. Tony agreed to schedule a meeting to get this figured
out.
AT&T: Manhole adjustment
at South street is being addressed by Tony. He spoke to Dennis and said that it
will be taken care of by the end of the day today.
Water Dept.: Ed does not
have the manpower to make the valve adjustments needed. Reith Riley is going to
look at the issues and work alongside Ed to either fix all of them or
prioritize the issues in the wheel path and fix those first. Also going to be
looking at taking hydrant valves and moving them to valve boxes.
Transpo: No issues, going
to be switching route to use Monroe and South. Reith Riley said that this would not be an issue.
Metronet: Items needed have
been shipped and are hoping to be installed on Monday or Tuesday of next week (8/1 or 8/2) and
should not take more than a day to complete.
MCI : Will be coordinating
with Reith Riley to set up a time late next week to make adjustments.
Utilites Q/A: Roger
had a question about the downtown wifi and is going to set up a meeting with
Martell to coordinate and sort out issues. There is an issues on Park lane by
the hospital with torn out areas of the wheelchair ramps with barrels over the
affected areas. No one was sure of what was happening and the city and Reith
Riley agreed to look into the situation.
10:00 am 10:10 Break Utility
and Stakeholders can leave
Submittals (List
at Meeting):
Action Items
1. Strain Pole Change Order: Good to go,
Scott will make edits to send to the board, Corbitt agreed to send an email
giving the ok to move forward.
2.
Saigon
Drive and Parking Lot: Started removing sidewalk and intersection face.
Owners would like for the sign to stay. The fence is being changed to a 3 ft
fence due to ordinance. Kevin, Scott, and Chris from Milestone fence to discuss
the new fence. New pavement in the lot should not take longer than a day to
complete and for the convenience of the owners it would be best to have the
work done on a Wednesday.
3. Signal
Cabinets/status: Still waiting
on prices for the cabinets. If the prices are obtained the issues will be
addressed in the current change order, if the prices are not obtained it will
be removed from the change order.
4.
Work
on East side of Main/shutting down: No issues
5. Chase Building Sidewalk and Access and
Construction: The header and curb are going to be put in and the rest
of the area is going to backfilled with stone. The sidewalk is not going to be
touched until April 2017.
6.
Heated
Sidewalks at Library: Roger
confirmed that the bike racks are out and the book drop has been moved so that
the sidewalks in front of the library can be removed. It was made a point to
note that not all of the sidewalk is being taken out, there is a small section
by the front door that is going to stay. Tony, Scott, and Myron agreed to meet
with the library to discuss issues with heated walks.
7.
Color
Approval for Splitter Islands: Corbitt approved and Chris Chockley from
JPR approved
8.
Water
valves adjust to grade: Walkthrough with City, Rieth-Riley, and
the Water Dept. is needed to determine scope
9.
Metronet
MH/Vault at NW Corner Marion/Main: Myron is going to call Ben Hudson
to discuss the issues.
10.
Block
detail for Permeable paver band: This issue was discussed and Roger
was going to draw up the new solution.
City
Concerns/Questions:
·
The fire hydrants on St Joe need moved out. Toy
and Rich are addressing this issue
·
Sign issue on Michigan: The sign does not fit
with current utilities. City agreed on the solution to talk to Metronet and
AT&T to see if either would be able to relocate. If this is not an option
next solution is to encase Metronet and install the sign. Myron and Rich both
agreed to push back installation until utilities have been sorted out.
·
Milling will begin after August 8th
from Marion North
·
Tentative plan for the mayor and council to walk
through some of the construction site.
·
Corbitt brought up also paving some of the side
streets while work is being done. Scott is going to look at the area and
evaluate options.
·
Marion plans call for decorative concrete in
bike path but it should be 5” concrete.
·
Someone needs to check bike path striping to be
consistent through the divisions.
Next weekly progress meeting 8-5-16