Wednesday, July 27, 2016

7-26-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Overcast PM Sunny
Hi 87 Lo 63

Rieth-Riley had a curb crew pouring curb for the southbound lanes of Main St. between South and Bronson.

A second Rieth-Riley crew pouring sidewalk on the east side of Main St. between Marion and Madison. In the afternoon they poured sidewalk on the west side of Main St. in frno of Fiddler's hearth and Madison Oyster Bar.

Indiana Earth removed sidewalk and curb on the west side of Main St. in front of Madison Oyster bar and Fiddler's Hearth.  backfilled the inside of the roundbaout walls at the Bartlett roundabout. 







No comments:

Post a Comment