Monday, July 18, 2016

7-18-16

Controlling Operation Bartlett: Roundabout Center Aprons
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 83 Lo 61
Weather Am Mostly Cloudy PM Mostly Sunny

Rieth-Riley had a concrete crew pouring the soundbound lanes of Main St. between South and Bronson. Pavement poured today went from approximately Line MAI Sta. 722+00 to Sta. 722+70. A 3-man grading crew graded the Transpo approach on the south side of South St. 

A second Rieth-Riley crew was pouring curb in the Marian section. Curb was poured on the north side of Marian between Line PR-A Sta. 22+65 to Sta. XX+XX.

Pemberton Davis poured foundations for light pole and signal poles at the intersection of Main St. and Washington. 

Indiana Earth had two removal crews working in the downtown section in the afternoon. A 2-man crew continued removals of pavement on the west side of Main between Washington & Colfax. A crushed concrete temporary drive was made for the alley near Fiddler's Hearth. The other 2-man crew backfilled and graded the southwest corner of the intersection of Main and Washington for curb. 

Ziolkoski finished the block wall to the Oyster Bar.