Monday, July 25, 2016

7-25-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
AM Overcast PM Sunny
Hi 84 Lo 61

Rieth-Riley had two concrete crew pouring sidewalk on the northwest and southwest sides of the Marian roundabout. In the afternoon they formed the section of sidewalk on the west side of Michigan between the Marion roundabout and Madison.

Indiana Earth backfilled inside the walls of the Bartlett roundabout.

Ziolkowski continued setting rebar cages and formwork for the concrete walls in the center of the Marion roundabout.

Pemberton Davis worked on light foundations on Main Street from Marion to Lasalle.