Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 86 Lo 67
Weather Am Overcast and Hot PM Overcast and Hot

Rieth-Riley had a concrete crew that poured the final sections of Bronson west of Main. The crew then moved to the Bartlett section and set forms for sidewalk on the west side of Michigan working north from Navarre.

Pemberton Davis installed the mast arm for the signal pole at the southwest corner of Michigan and Sample.

Ziolkowski continued setting forms for the concrete walls in the center of the Marion roundabout.

Reith Riley worked on sealing the Bartlett Street Round-about walls.

Indiana Earth worked on grading  out the sidewalk on the west side of Michigan between Bartlett and Navarre.