7-21-16

Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 94 Lo 77
Weather Am Overcast and Hot PM Overcast and Hot, Thunderstorms after 2 pm

Rieth-Riley had a concrete crew that poured the south lanes of Bronson St west of Main. They have a small portion of Bronson St. left to pour tomorrow. The crew also poured sidewalk on the west side of Main between Washington and Jefferson just south of the courthouse driveway.

Rieth-Riley also had a grading crew applying water-proof sealant to the inside of the roundabout walls at the Bartlett roundabout. 

Indiana Earth was at the Bartlett roundabout beginning to backfill inside the roundabout walls.

Ziolkowski was erecting wall formwork at the Marion Roundabout.

Pemberton Davis was installing tesco and signal cabinets at the intersection of Main and Washington.