Saturday, July 16, 2016

7-16-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 78 Lo 56
Weather Am Mostly Sunny PM Mostly Sunny

Rieth-Riley had a concrete crew pouring the southbound lanes of Main St. between South and Bronson. Pavement was poured from approximately Line MAI Sta. 720+30 to 722+00.

No other work was performed in Division B today. 