Tuesday, July 12, 2016

7-11-16

Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 89 Lo 63
Weather Am Mostly Cloudy PM Mostly Sunny

Rieth-Riley had a concrete crew pouring sidewalk and integral curb in the Bartlett section. Sidewalk was poured in the southwest corner of the roundabout and extends south to the crosswalk that crosses Michigan south of the roundabout. Curb was placed around the outside of the roundabout. The crew also poured the lower footing for the concrete steps south of Michigan west of the roundabout.

A second Rieth-Riley crew placed a temporary gravel crosswalk on the southwest corner of Main and Jefferson.

Indiana Earth removed sidewalk, curb, and pavement from the southwest corner of Main and Western in the morning. They also removed pavementfrom the southwest corner of Main and Jefferson. Another crew spent the day backfilling on the west side of Main between Lasalle & Colfax for the placement of curb.

Ziolkowski had a crew doing final preparations for the concrete wall pour in the center of the Bartlett roundabout that will take place in the morning (7/12).

In general, it was a very light day in Division B, with very limited work being done in the downtown area. Numerous areas of downtown have been removed and not yet put back.