Controlling Operation Bartlett: Wall Construction
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Storm Pipework
Fraction of Day workable 10/10
Hi 84 Lo 69
Weather Am Overcast and Humid  PM Overcast and Humid

Rieth-Riley had a grading crew that finished grading the intersection of Bronson and Main in the morning. This section is now ready for concrete pavement.

Rieth-Riley also had a concrete crew pouring sidewalk and curb ramps on Michigan north of the Bartlett roundabout, and a curb crew pouring curb at the intersection of Main and Madison and on Main St. between Madison and LaSalle.

Ziolkowski had a 5 man crew making final formwork preparations for the concrete walls in the Bartlett roundabout which are scheduled to be poured tomorrow (7/8).

Woodruff had a crew installing storm pipe and structures on the west side of the intersection of Main and Jefferson. Jefferson is closed to traffic but Wayne street is now back open.

Indiana Earth had a crew removing curb and sidewalk on the south side of South St. for the construction of the Transpo approach. A second Indiana Earth crew removed curb and sidewalk along the west side of St. Joe between Washington and Colfax.