Controlling Operation Bartlett: Roundabout Center Aprons and Curb
Controlling Operation Marion: PCCP Pavement
Controlling Operation Lasalle to Ewing: Curb
Fraction of Day workable 10/10
Hi 89 Lo 64
Weather Am Mostly Sunny PM Sunny, HOT

Rieth-Riley had a concrete crew which poured the remainder of South St and the north side of Bronson St. west of Main. In the afternoon they formed the south side of Bronson.

Rieth-RIley also poured the first two levels of flowable fill in the Madison Oyster Bar vault. 

Pemberton Davis finished their work at the intersection of Main and Washington.

Indiana Earth started removals on the east side of Main between Colfax and LaSalle.

Zoilkowski worked on forming the Marion Round-about walls.