Hi 68 Lo 44
Pemberton Davis worked on the intersection of Monroe and Main with a 6 man crew they hooked up the conduit for the new tesco. They dug the foundations for the new walk waits and ran conduit for the walk waits,
Reith Riley had 3 forman and 3 laborers cutting brick and placing them on the east side of Main street from Jefferson to Wayne.
Robert Henry helped get the power into the vault on main street between South and Monroe street on the west side of Main.
Meeting Agenda
Meeting With:
|
Reith
Riley & City of South Bend
|
|
|
Meeting Date:
|
|
|
|
Regarding:
|
Two
Way Conversion Weekly Progress Meeting
|
|
Construction and
Utilities
|
|
|
ITEMS TO BE
DISCUSSED
9:00 AM Introductions/Sign
in
The Weeks up Coming
Events/Schedule
1. Reith Riley:
will work on the brick pavers on Main Street and then bring in a concrete crew
starting next week and finish the sidewalk and ramps on Main Street first and
then move to MLK. At the same time, Indiana earth will come in, work on
removals on Main Street first, and then move to MLK.
2.
Pemberton Davis: will be working on Monroe and Main today and Monday and on
Monday they will fall back and finish western and main as soon as AEP get the
power terminated to the old Tesco. They will then be done with main street
traffic signals and move to Monroe and Michigan. Once on Michigan/MLK they will
work from the South to the North.
Utility Relocation Issues:
AEP:
1.
Disconnect power at Western and Main, This will
take place on Monday
2.
Disconnect power at MLK and Jefferson, This will
also take place Monday
3.
Disconnect power to MLK and Washington, This
will take place on Monday
4.
Disconnect power to MLK and Colfax, This will
take place on Friday with Phil coordinating with AEP.
Phil will make a list of the rest
of the disconnects so Toy can get with AEP so that there will be less trouble
in the future.
Robert Henry:
1.
Manhole lid at Main and LaSalle: Robert Henry is
still looking for a Riser but a job may need to be let and have the whole
structure raised.
Metronet:
1.
WIFI on Saint Joe and Main only to left Washington
and Colfax- Martell is working on Washington today and will work on Colfax at
the earliest next Friday due to the power at the corner.
Transpo: is going to look at the bus
timing to see if they can get out of their drive. Ryan Huebschman was up Friday
and worked on the timings. He may have to come back again.
311
Utilities Q/A : AEP/
Aldridge will have Michigan closed from Wayne to western from 4-13 to 4-14
INDOT: Questions: DID not attend
Stakeholder Questions:
Memorial Hospital: Biggest concern at this time the Bartlett crosswalk
being down
Action Items
1.
Colfax and Main Pole: Toy approved the pole,
Tanner needs to get the anchor bolts, he will check with ED Gleckler, if ED
doesn’t have them it will take around a week to get them in.
2.
Guardrail at underpass on Main Street. Rich
Zielinski from structure point was up yesterday and they are working on it
today and expect to have it to the city ASAP. Structure Point will check with
the Railroad
3.
Pave Drain low: a meeting will be held on
April 19th at 9am to discuss this further
4.
Majority Builders Sidewalk work; they have
not returned Jitin’s emails. Jitin will continue to press the issue with them.
Reith Riley needs to know asap in order to get the work done by June
5.
Chase tower still good to go April 1: Toy
assured Reith Riley they would have the scaffolding out of the way and no
overhead work would be taking place.
6.
Landscape work: Saint Joe irrigation was
verbally approved, the trees in the downtown area need attention, Josh will get
with the water department to get the meters installed for the Saint Joe irrigation.
7.
Pavement Marking Changes; Reith Riley is
aware of the changes at Sample and Michigan. The City is going to resurface
Wayne Street from so it can be temporarily painted. Green paint may be added to
the bike path at the garage entrances on Main Street.
8.
Crosswalk at Bartlett: the base to the
post that was struck is universal and can be changed out relatively ease. Work
should take place sometime next week.
Reith Riley Construction
Concerns/Questions
Reith Riley question how to detour traffic during the day
while they are doing the work in front of the school building. This may need to
wait until Colfax and main is completed.
City
Concerns/Questions:
Next weekly progress meet ? Will be April 7th
( Josh will be in charge from March 30th to April 9th)