Friday, December 16, 2016

12-16-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Snow PM Mostly Cloudy  
Hi 16 Lo 2

Reith Riley is shut down for the winter.

Pemberton Davis had a couple of guys working on signs.

No other work preformed today due to the cold temperatures wind chill below zero.

Thursday, December 15, 2016

12-15-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Snow PM Mostly Cloudy  
Hi 8 Lo -2

Reith Riley is shut down for the winter.

No other work preformed today due to the cold temperatures wind chill below zero.

Wednesday, December 14, 2016

12-14-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 3/10
AM Partly Cloudy PM Partly Cloudy  
Hi 18 Lo 2

Reith Riley is shut down for the winter.

Pemberton Davis had a crew come in and place signs north of LaSalle to Park on Michigan and Main. They came in after 12:00 pm

No other work preformed today due to the cold temperatures wind chill below zero.

Tuesday, December 13, 2016

12-13-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 5/10
AM Cloudy snow PM Cloudy  
Hi 26 Lo 15

Reith Riley is shut down for the winter.

Pemberton Davis did not work in the morning due to the snow. Around 11:00 am they had a 6 man crew work on the street lights on the east side of Saint Joe between jefferson and Colfax. 

State Barricade was on site and picked up more Barrels that where not being used.

No other work today

Monday, December 12, 2016

12-12-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Signals
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 5/10
AM Cloudy  PM Cloudy  
Hi 31 Lo 15

Reith Riley is shut down for the winter.

Pemberton Davis did not work due to the heavy snow over night the streets still needed cleaned. 

No other work today

Friday, December 9, 2016

12-9-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Snow PM Cloudy Snow windy 
Hi 25 Lo 15

Reith Riley had a crew on site cleaning up blankets and pallets and bricks. A second crew worked on saw cutting brick on the east side of Main Street down by the library. They also worked on cleaning drains that where plugged due to the milling operation.

Pemberton Davis was not on site today.

State Barricade picked up more barrels and did general clean up.

Thursday, December 8, 2016

12-8-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Snow PM Cloudy Snow windy 
Hi 27 Lo 15

Reith Riley had 3 prep crews on site today working on cutting brick and placing brick on Main Street from Colfax to Western on the east side of the road.

Slussers had a crew in working on placing dirt around the trees on main street from LaSalle to Western on both sides of the road.

Pemberton Davis worked on Cleaning up for the snow and went home at noon.

State Barricade opened Bronson Street up at 7:30 am. They then worked on picking up excess barrels.

Wednesday, December 7, 2016

12-7-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy 
Hi 37 Lo 27

Reith Riley has a concrete crew working on ramps at the south west corner of Main and Western. They have a second crew working on the south east corner of Jefferson and Saint Joe at the Century center. A third crew is pouring in the water preventer valves for the irrigation and various pieces on Michigan from Washington to Navarre.

Reith Riley had a brick crew working on Main street on the east side from Colfax to LaSalle cutting. A second crew was working from ColFax to Washington cutting and placing brick. A third crew was working from Jefferson to Western placing stone on the east side of Main for brick subbase.

Slussers was on site planting trees on the west side of Main from LaSalle to Western,

Pemberton Davis was stinging cable and setting heads at the intersection of Jefferson and Saint Joe.

Tuesday, December 6, 2016

12-6-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy  PM Cloudy 
Hi 40 Lo 30

Reith Riley had a concrete crew working at the South West corner of Main and Western. a Second crew is working on the South West corner of Jefferson and saint Joe they then went to the South east corner of Jefferson and saint Joe, A third crew worked on the South east corner of Michigan and Jefferson/Wayne, They then worked on the South West corner of Jefferson/Wayne and Michigan. 

Reith Riley had a crew placing brick on the south west corner of Colfax and Main. A second crew worked on Main Street from Jefferson to Wayne on the east side. 

Indiana Earth was working on the paver base at the intersection of Jefferson and Saint Joe.

Pemberton Davis worked on setting strain poles at the intersection at of Jefferson and Saint Joe. They also worked on conduit at Western and Saint Joe. They were also installing the pucks for the LaSalle/Main street intersection.

Slussers was on site and planted trees on Main a street from LaSalle to Wayne on the west side of the road,

Air Marking was in and Temporary stripped the turn lane on Sample and they temporary stripped Madison from Lafayette to Michigan. 

12-5-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Mostly Cloudy PM Mostly Cloudy
Hi 38 Lo 32

Reith Riley had a Concrete crew working on the South West corner of Western and Main. A second crew worked on the South east and North east corners of Main and Monroe. 

Reith Riley had multiple crews working on the brick on Main street from LaSalle to Western on the east and west side of the road. 

Pemberton Davis moved the Tesco at Western and Main. They also worked on pouring the foundation at Jefferson and Saint Joe.

Indiana earth began filling in side walk areas that could not be finished this year.

Air Marking was in and did more grinding on Sample Street east of Michigan

12-3-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Sunny PM Sunny
Hi 42 Lo 30

Air Marking had a crew on site and stripped the side streets of western, Colfax, LaSalle ,Wayne and Jefferson. A second crew worked on detail work at Sample, Western and Main Street.

No other work took place today.

Friday, December 2, 2016

12-2-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Drizzle PM Cloudy Drizzle


Hi 38 Lo 32

Reith Riley had a concrete crew work on pouring the North East and South west corner of Michigan and western. A second crew worked on miscellaneous pours through out the job all the way to Angela. 

Reith Riley had a brick cutting crew working on the west side of main from Wayne to Western. a stone crew worked the east side of main between Jefferson to Washington. A brick laying crew worked the east side of Main from Jefferson to Washington.

Indiana earth worked on cutting out from LaSalle to Madison on the east side of Michigan for brick. They then cleaned up South of LaSalle on Saint Joe on the east side.

Slussers placed sod on Main Street from Madison to LaSalle on the east and west side. They then worked on Michigan from LaSalle to Marion on the east and west side of the road.

Pemberton Davis poured the foundations on the east side of Saint Joe at Jefferson. They also worked on the conduit at western and Main South west corner.

Air Marking was on site and did removals at western and Main on Lafayette and LaSalle they also did removals on sample east of Main. 


Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
12-2-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Traffic Closure Updates: Crews will just be closing a lane where they are working and putting out barrels to direct traffic around them. Pemberton Davis will be closing Washington Street when they do signal work there for safety.

Utility Relocation Issues:
AEP:   Was not at the meeting

Robert Henry: Was not at the meeting
1.       Michigan St. will be open by 4pm today for the weekend and will close again on Monday.
2.       Vault at Main and Washington S/E  Corner

NIPSCO/InfraSource:   Was not at the meeting

Water Dept:   Had questions about snow removal at their office on Main and Colfax. Everything should be fine, and they were asked to keep the salt use to a minimum

Transpo:    Asked about light timing, which will be an ongoing process and when the traffic signal at Michigan and South street will be in. Hopefully by Christmas.
               
Metronet:  Was not at the meetin
 1.  WIFI  on Saint Joe and Main. Nothing has been done with this yet.
                 

Utilities Q/A:  Grinding and striping was brought up on Sample St. which should be happening today. 311 also asked about left turn lanes on Sample to turn onto Michigan and Main streets. This has to happen through INDOT though because it is a state highway.

INDOT: Questions:   

Stakeholder Questions: The signs on Michigan by Angela heading south that say the road is open to the hospital can now come down. The hospital asked when the railings for the stairs and gate for dumpster pad are going in. Measurements have been taken and they are being fabricated off site. The no parking signs on Bartlett are to be put back up. The hospital also wanted to know when the striping for the parking garage entrance will be done, which may not happen until spring. They also asked to check if the project has outlets going in next to the trees for Christmas lights.

10:00 am 10:10 Break Utility and Stakeholders can leave


Action Items
               
1             Upcoming work for the week: Brick pavers on Main St. and curb ramps on St Joe/Michigan. Pemberton Davis will be working on traffic signals.
2             Western and Main South West Corner: Will start on Monday, should be done by Wednesday
3             Scheduled \opening
     A. Traffic Signals Jefferson\Washington: Beginning work on Jefferson on Wednesday, and Washington right after that. They will be closing Washington between Michigan and St. Joe while working on the intersection.
     B. Markings: Trying to get in the most important ones before winter.
4             Chippewa walk trough/ Traffic signal work: The walk through will be Wednesday Dec. 7th from 1-3pm. Meeting in the Palmer funeral home parking lot
5             Snow Flags have been ordered and are at the border waiting to come through customs.
6             Main Street Bridge lighting: Pemberton Davis will have a quote in today and once it is approved will order the lights and install them as soon as they come in. One to two day project, and will have a separate service crew installing them.
7             Getting ready for Winter/expectations
A.      Cross walks: Hope to have one concrete one in at each intersection. Will keep working on them and temporarily fill with stone any that don’t get poured before winter.
B.      Clean Man Holes: On the list of things to do
C.      Temp Tape removal on the list of things to do
D.      Behind curb drop-offs
E.       Signs on 31 will be taken care of. Didn’t take them down this week because of concerns of getting stuck in the ditch with how rainy it has been.
       
Reith Riley Construction Concerns/Questions: Will need access to the area in front of the Chase tower and the new Marriott hotel by May 1st in order to complete everything by June 1st

City Concerns/Questions:  Made sure that Pemberton Davis will work on getting street lights up on one side of St. Joe before finishing the second side of Main St.
                               
 Next weekly progress meeting ?




Thursday, December 1, 2016

12-1-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Drizzle PM Cloudy Drizzle
Hi 38 Lo 32

Reith Riley had a concrete crew pour the south west corner of Monroe and Saint Joe. A second Crew poured the North east corner of Saint Joe and Colfax and they poured the south east corner of South and Michigan.

Reith Riley had a prep crew working on the west side of main Street cutting brick from Wayne to Jefferson. A second crew worked on brooming in sand on the west side from LaSalle to Jefferson. A third crew set block from Colfax to Washington on the east side.

Pemberton Davis poured Strain pole foundations at Jefferson and Saint Joe. They worked on the South West corner of Western and Main.  

Indiana earth worked on demoing the curb at western and Main on the South west corner. They also worked on grading various areas threw out the project.