Thursday, December 8, 2016

12-8-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Snow PM Cloudy Snow windy 
Hi 27 Lo 15

Reith Riley had 3 prep crews on site today working on cutting brick and placing brick on Main Street from Colfax to Western on the east side of the road.

Slussers had a crew in working on placing dirt around the trees on main street from LaSalle to Western on both sides of the road.

Pemberton Davis worked on Cleaning up for the snow and went home at noon.

State Barricade opened Bronson Street up at 7:30 am. They then worked on picking up excess barrels.