Thursday, December 1, 2016

12-1-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Cloudy Drizzle PM Cloudy Drizzle
Hi 38 Lo 32

Reith Riley had a concrete crew pour the south west corner of Monroe and Saint Joe. A second Crew poured the North east corner of Saint Joe and Colfax and they poured the south east corner of South and Michigan.

Reith Riley had a prep crew working on the west side of main Street cutting brick from Wayne to Jefferson. A second crew worked on brooming in sand on the west side from LaSalle to Jefferson. A third crew set block from Colfax to Washington on the east side.

Pemberton Davis poured Strain pole foundations at Jefferson and Saint Joe. They worked on the South West corner of Western and Main.  

Indiana earth worked on demoing the curb at western and Main on the South west corner. They also worked on grading various areas threw out the project.