Wednesday, November 30, 2016

11-30-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 55 Lo 42

Reith Riley had a concrete crew working on the South East corner of LaSalle and Saint Joe pouring sidewalk and finishing the curb. A second crew worked on the South east corner of Colfax and Main and Jefferson and Main. That crew also raised manholes in various locations.

Reith Riley had a prep crew cutting block on the west side of main from Jefferson to Wayne. A second crew placed brick on the east side of Main from Colfax to Washington. A third crew prepped stone on the east side of main from Washington to Jefferson. A fourth crew placed the paver bands on Michigan from Marion to LaSalle on the east side.

Pemberton Davis worked on pouring Strain pole foundations at Jefferson and Saint Joe, they also worked on pouring cabinet and tesco foundation on the south west corner of Main and Western. They worked on the traffic signals at the intersection of LaSalle and Michigan. They also removed the light on the North West corner of Main and Colfax.

Indiana Earth worked on grading out the corners of Jefferson and saint Joe. 

No comments: