Monday, November 21, 2016

11-21-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny PM Sunny

Reith Riley had a concrete crew working on the South east and North east corner of Colfax and Saint Joe they poured the curb and pavement at these corners. A second crew worked on pouring cycle track on the east side of Saint Joe between Colfax and LaSalle on the east side they also poured a small piece around the AEP manhole on the west side of Saint Joe.

Reith Riley had a prep crew working on the cycle track on the South side of LaSalle just east of saint Joe. A second crew worked on placing stone on the west side of Main Street between Wayne and Jefferson. A third crew placed brick on the west side of main between Wayne and Washington.  

Pemberton Davis worked on setting the Tesco and Signal cabinets at the intersection of Colfax and LaSalle on Saint Joe Street. They also set light foundations on the east side of saint Joe between Colfax and LaSalle, 

WISCO worked on the irrigation on main Street between Madison and LaSalle on the west side.

Air Marking had a crew laying out and doing removals on the side streets. A second crew worked on the details on saint Joe between Marion and Bronson.