Thursday, November 3, 2016

11-3-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Cloudy  PM partly Cloudy 
Hi 64 Lo 58

Reith Riley had a concrete crew work on the South East corner of Wayne and Main. They had a second crew working on the cycle track in font of the library. A curb crew worked on the east side of Saint Joe from LaSalle to Colfax. A fourth crew worked on the South west corner of Saint Joe and the Morris drive doing sidewalk.

Reith Riley had a prep crew working on placing the 8's on the west side of Main from Wayne to Jefferson. A second prep crew worked on saint Joe street. 

Indiana earth continued to do removals on the east side of Saint Joe from Washington to Colfax. They also worked on grading on the east side of Main street between the curb and sidewalk,

Pemberton davis worked on the east corner of Main and Wayne. They also worked on setting pole foundations on the east side of Saint Joe from LaSalle to Wayne.

Slussers was in and planted trees at Bartlett west of Michigan. 

Wisco continued to work in front of McDonald's.

No comments: