Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny PM Sunny
Hi 54 Lo 29
Reith Riley had a crew on main street placing brick on the west side between LaSalle and Washington. A second crew worked on prepping the stone in front of the brick.
Reith Riley had a prep crew placing asphalt in front of the curb on Saint Joe and LaSalle prepping for paving tomorrow.
Reith Riley had a concrete crew wo
Indiana earth was working on placing soil in for the sidewalk areas between Jefferson and Main and a second crew working between Colfax and Washington.
Slussers is on site working on planting trees on Marion east of Michigan and on Michigan south of Marion.
Zoilkowski is on site rubbing the concrete for the roundabout at Marion.
Pemberton Davis is working on the signal at the intersecton of Bronson and Michigan. they then moved to the intersection of Saint Joe and Colfax.