Wednesday, November 16, 2016

11-16-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 63 Lo 36

Reith Riley had a concrete crew pouring cycle track on the east side of Michigan just North of LaSalle. A second crew worked on cycle track just south of Jefferson on the east side of saint Joe. A Third crew worked on Cycle track between Jefferson and Washington on the east side of Saint Joe.

Reith Riley had a prep crew grading out for sidewalk on the east side of Saint Joe between Colfax and LaSalle. A second crew worked on placing brick on Main street between Colfax and Jefferson on the west side of the road. 

Indiana Earth worked on removing foundations on the east side of Saint Joe between Wayne and LaSalle. A second crew worked on placing dirt in the islands on saint Joe between Wayne an LaSalle.

Wisco worked on the irrigation between Washington and Colfax on the east side of Saint Joe.

Zoilkowski worked on rubbing out Marion Roundabout and the Bartlett Roundabout.

Pemberton Davis worked over night on the intersection of Colfax and Main swapping out cabinets and removing poles. Then during the day they worked on removing all the poles at Colfax and Saint Joe.