Tuesday, November 15, 2016

11-15-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 58 Lo 34

Reith Riley had a concrete crew working on placing the Herringbone brick on the west side of Main street between LaSalle and Washington. A prep crew worked out in front of them grading out the number 12 aggregate base. 

Reith Riley had an Asphalt crew on site paving at the intersection of LaSalle and saint Joe. They also did some miscellaneous work on the side streets patching. 

Reith Riley had a Concrete crew working on the Cycle track between Jefferson and Wayne on the east side of Saint Joe. A second crew worked on Cycle track between Washington and Jefferson on the east side of Saint Joe.

Indiana Earth worked on grading out for side walk on the east side of Saint Joe between Wayne and Jefferson. They also had a crew working on placing 53 base for the herringbone on the east side of Main street from Colfax to LaSalle.

Zoilkowski was on site rubbing out the Bartlett round about. 

Pemberton Davis was working on placing the heads on the intersection of Colfax and Saint Joe. They also placed conduit on the east side of saint Joe between Washington and Colfax.   