Wednesday, November 2, 2016

11-2-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Partly Sunny  PM Cloudy 
Hi 71 Lo 58

Reith Riley has a concrete crew pouring the cycle track from Wayne to Western on the East side of Main Street. A Second crew is pouring the South East corner of Main and Wayne. A third crew worked on pouring side walk on the west side of saint Joe between Morris drive and LaSalle. When they were done with that they worked on finishing the center islands on Saint Joe between Wayne and LaSalle.

Air Marking is working on striping from Sample ton Monroe on Michigan. They also had a detail crew working on Michigan between Sample and Monroe on Michigan. They had a crew doing removals on the side streets between Lafayette and Saint Joe.

Reith Riley had a prep crew placing 8's and filter cloth for the brick pavers between LaSallle and Wayne on the west side of Main. A second prep crew worked on resetting the tree grates on Main Street.

Pemberton Davis worked on digging and pouring foundations for light poles and strain poles on Saint Joe street from LaSalle to Wayne on the west side of the road. They also worked on placing conduit from foundation to foundation. They had a second crew working on the pucks at the intersection of Michigan and North Shore. They had a crew pushing conduit at Angela and Michigan for the new detector housings.

Woodruff changed some grates around and moved things around and then went home because nothing was ready for them to work on.

Indiana Earth worked on grading out between the curb and side walk on the east side of main street from LaSalle to Western. They also had a second crew on the east side of Saint Joe doing removals from Jefferson to Colfax.

Wisco was on site working on the east side of Michigan between Marion and Madison.

Reith Riley had a Milling crew come in late and mill the patch on Main at Monroe and the water hole on Wayne east of Main and the parking lot/alley between Jefferson and Wayne.