Wednesday, November 9, 2016

11-9-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Cloudy Sunny 
Hi 59 Lo 42

Reith Riley had a concrete crew working on the North east corner of Western and Main. They had a second crew working on the drive to the art museum on saint Joe. A third crew worked on the island curbs between LaSalle and Colfax on Saint Joe. they had a fourth crew pouring curb on the east side of saint Joe between Colfax and Jefferson.

Reith Riley had a prep crew placing asphalt between the curb and pavement on Saint Joe between Wayne and LaSalle on the east side of the road. A second crew worked on the paver's between Madison and LaSalle on Michigan.  A third crew worked on Main street placing stone for the brick pattern.

Indiana Earth had a crew placing fill in behind the curb on Saint Joe. between Wayne and Jefferson. A second crew worked on grading between LaSalle and Colfax. They also removed trres on Michigan between Navaree and Bartlett. 

Slussers was on site and planted trees between Marion and Bartlett on Michigan.

Woodruff worked on the last of the structures and meter between Jefferson and LaSalle on the East side of the road.

Pemberton davis worked on Setting street lights on the east side of Main Street between LaSalle and Jefferson. They worked on placing conduit at the intersection of Michigan and Monroe and along the west side of saint Joe between Washington and Colfax on the west side of the road, They also worked on the South west corner of Saint Joe and LaSalle.