Friday, November 18, 2016

11-18-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Cloudy rain Late
Hi 72 Lo 46

A car hit 2 light poles and 4 tree grate boxes on the west side of Main Street between Jefferson and Wayne.

Reith Riley had a concrete crew working on pouring cycle track on the east side of saint Joe from Colfax to LaSalle. A second crew finshed pouring cycle track on the east side of saint Joe from Washington to Colfax.

Reith Riley had a prep crew working on the west side of Main street placing decorative brick between Wayne and Washington.

Wisco worked on the irrigation between Madison and LaSalle on the east side of Michigan.

Pemberton Davis worked on the intersection of Monroe and Michigan, they also worked on pouring light pole foundations between LaSalle and Wayne on the east side of saint Joe.   

Airr marking was on site working on Saint Joe, LaSalle and colfax, until the truck broke down around 1:00pm. A second crew worked on lay out and a third crew worked on detail work.


Meeting MINUTES
Meeting With:
Reith Riley & City of South Bend


Meeting Date:
11-18-16


Regarding:
Two Way Conversion Weekly Progress Meeting

Construction and Utilities



ITEMS TO BE DISCUSSED

9:00 AM Introductions/Sign in

The Weeks up Coming Events/Schedule
1.       Traffic Closure Updates
A.       Saint Joe will open from Western to Sample on Tuesday, and LaSalle to Western Wednesday afternoon (11-23-16). The traffic signal at Bronson and Main won’t start until Dec. 1st.

Utility Relocation Issues:
AEP:        Jefferson and Michigan will be open for the weekend, and then closed again Monday-Wednesday. After Wednesday only southbound Michigan between Jefferson and Wayne will be closed.

Robert Henry:
1.       Washington and Michigan is done and paved.
2.       Vault LaSalle and Michigan N/W Corner has been approved to work on, will coordinate time with Rieth-Riley
3.       Vault at Main and Washington S/E  Corner work will begin the 2nd week in December and be done the 1st week in January
4.       Casting west side of Saint Joe by Morris is done.

NIPSCO/InfraSource:   
            
Comcast: 

                AT&T:     

Water Dept:   Has received as builts from Woodruff. Also concerned that some hydrants might be too high, and will get Rieth-Riley a list of ones of concern

Transpo:    Had questions about signal timing and when the signal at South St and Michigan will be up.
               
Metronet:  Not at meeting
 1.  WIFI  on Saint Joe still has not been moved
2.       Foundation at Century Center removed
                 

Utilities Q/A

INDOT: Questions:   

Stakeholder Questions: The hospital asked about a walkway from their parking lot east of Michigan. Rieth-Riley put one in near the Marion roundabout crosswalk but they would like one further north for people heading to Navarre. They also had questions about the pedestrian signs north of Bartlett and putting the signs laying on the ground back up. They worried about the drop off on the edges of the sidewalk, but sod should be in everywhere from LaSalle north this year.

10:00 am 10:10 Break Utility and Stakeholders can leave


Action Items
               
1             Upcoming work for the week: Decorative brick along Main St. pouring sidewalk and opening St. Joe to two way traffic
2             Western And Main South West Corner: JPR will lay it out
3             Scheduled \opening
     A. Traffic Signals- Colfax and LaSalle today and tomorrow
     B. Markings- St Joe will hopefully be done by the end of the day.
4             Chippewa walk trough/ Traffic signal work: 30 mph signs in today, walk through first week in December
5             Snow Flags- Will take a couple weeks to order, will come up with a count
6             Landscape Sod and Trees- North of LaSalle will be done this year, trees down Main St. may be questionable to get in this year.
7             Main Street Bridge lighting- Pemberton Davis to get a quote next week. Will not do the work until bridge is no longer populated by homeless people for safety concerns.
8             Getting ready for Winter/expectations
A.      Cross walks- One concrete crew will be staying onboard as long as the weather holds out to continue getting as many curb ramps in as they can before winter.
B.      Clean Man Holes- before winter
C.      Temp Tape- to be removed
D.      Behind curb drop-offs- Stone and 8’s will be in so it will only be around a 4 inch drop. Fiberglass markers will be put up to show where the drops are for vehicles plowing the sidewalk and cycle track.
E.       Planters at the court house- DTSB to move
Reith Riley Construction Concerns/Questions:

City Concerns/Questions: The city wants to make sure the century center is accessible through the winter, with walks at Jefferson and Washington. They would also like the curb ramps that have been torn out for months filled in at Western and Monroe/Michigan. Rieth-Riley will work with Pemberton Davis, and have them finish work in the ones that need the least done in order to be able to pour the most curb ramps possible before winter.

The order decided on for installing traffic signals is to do Jefferson/St. Joe, then LaSalle/Main and LaSalle/Lafayette, then Washington/St. Joe
                               
 Next weekly progress meeting 11-18-16