Tuesday, November 22, 2016

11-22-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Cloudy PM Cloudy
Hi 41 Lo 27

State Barricade opened up Michigan to two way traffic from Western to Sample at 1:30 pm. 

Reith Riley had a concrete crew finish the sidewalk between Colfax and LaSalle on the East side of Saint Joe. A second crew worked on the north side of LaSalle east of Saint Joe pouring sidewalk.

Reith Riley had a prep crew on the west side of Main street between Wayne and western placing stone for decrative brick. They had a second crew placing brick on the west side of Main Street between Wayne and Jefferson. A third crew was cutting brick on the west side of main between Washington and Jefferson. A fourth crew worked on prepping for side walk at the North west corner of saint Joe and Colfax, South east corner of Colfax and Main and South west corner of Colfax and Main.

Air Marking had a detail crew on site doing arrows and only's. They had the long line truck on site doing side streets and finishing Saint Joe.

Slussers was placing sod on Main street between Marion and LaSalle on the east side of the road.

Pemberton Davis worked on the intersection of Monroe and saint Joe over night. Today they worked on the traffic signals at the intersection of Western and Saint Joe. They set the pole and heads at the intersection of LaSalle and Saint Joe. They poured the foundation for the tesco and cabinet at Colfax and saint Joe. 