Thursday, November 17, 2016

11-17-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 68 Lo 46

Reith Riley had a concrete crew finish the cycle track between Wayne and Jefferson on the east side of Saint Joe. A second crew worked on finishing the cycle track between Washington and Jefferson on the east side of Saint Joe. A third crew worked on the cycle track on the east side of Saint Joe between Colfax and LaSalle. 

Reith Riley had a prep crew working on the east side of Michigan between LaSalle and Madison. A second crew worked on Main Street placing decorative brick and stone chips and sanding in the brick.

Indiana earth had a crew on Saint Joe removing foundations between Wayne and LaSalle on the east side of the road. A second crew worked on the east side of Main Street placing 53s for the decorative brick.

Air marking had 3 crews on site, one crew worked on doing the layout on Saint Joe from Sample to Marion. A second crew worked on stripping the long lines on saint Joe. the third crew worked on the detail work on Saint Joe. Airmarkings long line truck broke down at noon.

Pemberton Davis worked on setting the poles on the South West corner of Western and Saint Joe. They then moved to the corner of LaSalle and Saint Joe and worked on Hangers and disconnects. They also worked at the North east corner of Colfax and Saint Joe placing conduit and handhole. They also dug the foundations for the poles at the intersection of Wayne and Saint Joe. 