Wednesday, November 23, 2016

11-23-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Rain PM Rain
Hi 45 Lo 34


Reith Riley had a crew cleaning up Saint Joe and main Street for the Holiday weekend. they left at 11:00 due to the rain.

Pemberton Davis removed the poles at LaSalle and Saint Joe Street. They took down the one way signs on Saint Joe between Western and Marion. Then went home due to the rain.

Indiana Earth worked on main Street placing stone between Western and Wayne on the east side. 

Satate barricade was on site and opened the last leg of Saint Joe between Western and Marion at Noon.