Thursday, November 10, 2016

11-10-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 62 Lo 36

Reith Riley had a concrete crew working on the curb that needed tied in on Saint Joe between Jefferson and Colfax on the east side. They had a second crew working on the sidewalk on the east side of saint Joe between Colfax and LaSalle.

They had 2 prep crews placing asphalt between the curb and road on the east side of saint Joe from Jefferson to Colfax. A third crew worked on main street placing aggregate for brick pavers.

Reith Riley had a milling crew on Saint Joe Street from Western to LaSalle milling off the surface.

Wisco was on site placing sleeves on Saint Joe for the irrigation.

Slussers was on site planting trees on Main Street and Michigan and the Marion Round about.

Woodruf worked on the water tapes on Saint Joe Street for the irrigation one on LaSalle and one at the Century Center.

Pemberton Davis worked on setting strain Poles at the intersection of LaSalle and Michigan and Colfax and Saint Joe. They also worked on setting light poles on Main street. They also worked on doing conduit on saint Joe west side.