Monday, November 7, 2016

11-7-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Removals
Fraction of Day workable 10/10
AM Sunny  PM Sunny 
Hi 69 Lo 42

Reith Riley had a concrete crew working on the South West corner of Main and Western. A Second crew was working on the ramps in front of the library. A third crew worked on the cycle track on the east side of Michigan from Madison to LaSalle.

Reith Riley had an Asphalt crew working on paving the intersection of Main and Monroe, Main and Washington, the alley between Jefferson and Wayne and the Saigon parking lot.

Reith Riley had a prep crew working on the stone for bricks on Main Street. a Second crew worked on grading for side walk north of LaSalle on Michigan.

Indiana Earth continued to do removals on saint Joe between Washington and Colfax. A second crew worked on Saint Joe removals between Wayne and Jefferson. a third crew worked on grading between LaSalle and Colfax behind the curb on the east side.

Slussers was on site and planted trees on Bartlett Street from Riverside to Michigan and North of Bartlett on Michigan. 

Wisco was on site doing repairs.

Pemberton Davis worked on the foundations at the intersect on of LaSalle and Michigan and Colfax and Saint Joe.

Air Marking not on site

No comments:

Post a Comment