Wednesday, November 30, 2016

11-29-16

Controlling Operation Bartlett: Lighting and Signage
Controlling Operation Marion: Lighting and Signage
Controlling Operation LaSalle to Ewing on Main: Traffic Markings
Controlling Operation LaSalle to Ewing on Saint Joe: Signals
Fraction of Day workable 0/10
AM Rain/sunny PM Sunny
Hi 58 Lo 41

Air Marking was unable to work due to the roads were wet until 10:00 am.

Reith Riley had a concrete crew working on the North West corner of LaSalle and Michigan. They also had a concrete crew working on the North East corner of Colfax and Saint Joe. They then went to the South west corner of Main and Colfax.

Reith Riley had a prep crew working on cutting brick from Jefferson to Washington on the west side of Main. They had a second crew working on setting block from LaSalle to Colfax on the east side of Main. A third crew worked on grading stone on the east side of Main from Colfax to Washington.

Indiana Earth worked on removing light pole foundations on the west side of Saint Joe from LaSalle to Jefferson. They also worked on grading stone on the east side of Main Street.

Pemberton Davis worked on the intersection of LaSalle and Main rewiring to the disconnects. They also worked on repairing the conduit at Colfax and Main South west corner that Indiana earth had hit. They also placed conduit at Colfax and Saint Joe North west corner for the power.

Slussers was on site prepping for sod on Michigan and Marion. They also planted bulbs in the Marion and Bartlett round abouts. 